Scrap % in Item Card and Production BOM Lines
Take this example, in order to produce 1 unit of Item A, you need 5 units of Item X.
If you set:
Scrap % in Item Card = 5
Scrap % in Production BOM line = 5
What does this means ? How will it affect your production planning. Let's say, you want to produce 100 units of Item A. 5% Scrap in Item Card means that, in order to produce 100 units of Item A, you need to produce 105 units because 5 units will be scrapped. In order to produce 105 units of Item A, you need 105 x 5 = 525 units of Item X. Because of 5% scrap in BOM, you need to add another 5% (26.25) of Item X in order to produce 105 units of Item A. Therefore, in order to produce 100 units of Item A, you need 525 + 26.5 = 551.25 units of Item X.
In order words, the Scrap% field on a BOM line represents components to be scrapped during production, while the Scrap% field on an item card represents output to be scrapped output (before putting on inventory).
* My company do not use Scrap % in both Item Card and Production BOM
Saturday, 13 October 2007
Setup Item Card for Requisition Management
Important fields to take note in the planning tab are:
Reordering Policy
Navision uses reordering policy field to calculate replenishment order quantity.
Fixed Reorder Quantity tell Navision to always take value in the Reorder Quantity field as proposed replenishment quantity. If Maximum Quantity is selected, Navision will calculate the proposed quantity that need to be purchased so that the replenishment will make the inventory level back to the maximum level. If Order is selected, Navision will propose one replenishment based on the requirement in sales order. If you do not select any reordering policy, Navision will not propose any replenishment for the item.
Reorder Cycle
This field accept a date formula that set the planning time frame. Reorder Cycle will be disabled if the Reordering Policy is set to Order. It is also not recommended to use Reorder Cycle together with Maximum Qty. reordering policy.
Reorder Point
Reorder point is the point where you must replenish the item if the quantity of stock fall below the reorder point. If the projected available balance fall below reorder point but still above the safety stock quantity, Navision will create a purchase order proposal that is forward scheduled until the day that cause projected available balance to fall below reorder point.
Safety Stock Quantity
Safety Stock Quantity is the quantity of stock that you want to keep in your inventory to prevent the situation of running out of stock. Inventory level will reach Reorder Point before reaching Safety Stock Quantity so that the items can be replenished before it fall below Safety Stock Quantity. If the projected inventory level already fall below the safety stock quantity, Navision will propose to at least replenish up to the Safety Stock Quantity.
Reorder Quantity
Value in Reorder Quantity field will be used in all replenishement proposal for the item selected. Whenever the item need to be replenished, the item will be replenished with the quantity specified int the Reorder Quantity field.
Safety Lead Time
Safety Lead Time is the safety time buffer to protect against delay in replenishment. Safety Lead Time will push the Expected Receipt Date in Purchase Line to a date later than the Planned Receipt Date.
Expected Receipt Date = Planned Receipt Date + Inbound Warehouse Handling + Safety Lead Time.
Maximum Inventory
Maximum Inventory is the maximum quantity you want to keep in your inventory. Navision will use this field to calcualte the quantity to be replenished if you choose Maximum Quantity in Reordering Policy.
Minimum Order Quantity
Minimum Order Quanitty is the minimum quantity to be purchased at purchase order. You cannot set a quantity in purchase order line that is smaller than the Minimum Order Quantity.
Maximum Order Quantity
Maximum Order Quanitty is the maximum quantity to be purchased at purchase order. You cannot set a quantity in purchase order line that is greater than the Maximum Order Quantity.
Friday, 14 September 2007
Item Category Code in Item Card
- General Product Posting Group
- Inventory Posting Group
- SST Product Posting Group
- Costing Method
Thursday, 13 September 2007
Last Direct Cost field in Item Card
Unit Cost field in Item Card
How Navision update the Unit Cost field is depends on what costing method used for the item.
1) Standard Costing - Unit Cost will be copied from Standard Cost field. Unit Cost will be updated when you change the value of Standard Cost. If you change the value in the Unit Cost field, the Standard Cost field will be updated as well.
2) Other Costing methods - Use the following formula:
Unit Cost = Inventory Value of Item on hand (cost expected + cost invoiced) / Quantity on hand
If you are not using Standard Costing, Navision will only update the Unit Cost field when you run Adjust Cost-Item Entries.
Besides updating the Unit Cost based on the above formula, Navision will also update the Unit Cost with the value in Last Direct Cost field in Item card when post purchase order as invoiced if one of the following conditions is met:
- Net invoiced quantity changes from negative to zero or positive.
- Unit Cost in Item card is zero -
The cost captured in the Unit Cost field is the total of both direct and indirect cost. The direct cost consist of the actual cost for the item purchased while the indirect cost may consist of the overhead cost such as insurance, handling and trasportation cost. If you can idenfity and want to maintain the indirect cost for the item seperately, you can use either one or both of the Overhead Rate field and Indirect Cost % field to capture the indirect cost. For example, the direct cost for Item A is $0.80 and the indirect cost is $0.20. You need to enter $1.00 in the Unit Cost field and $0.20 in the Overhead Rate field. Please note that the Unit Cost is $1.00 ($0.80 + $0.20). Navision will be able to calculate the direct cost for you automatically while doing posting based on the information in the Overhead Rate and Indirect Cost % fields.
Average Cost (LCY) field in Item Card
1) Post Invoice
2) Inventory Increase
3) Inventory Decrease
4) Adjust Cost - Item Entries
The formula used to calculate the Average Cost (LCY) is as follow:
Average Cost (LCY) = (Cost Amount (Actual) + Cost Amount (Expected)) / Total Item Ledger Entry Quantity
Saturday, 30 June 2007
Auto Populate VAT Prod. Posting Group from Gen. Prod. Posting Group
Update Unit Price in Item Card
The SQL statement generated from my test data is as follow.
UPDATE "CRONUS Malaysia Sdn_ Bhd_$Item" WITH (REPEATABLEREAD) SET "Unit Price"=2.7,"Profit %"=48.14815,"Last Date Modified"={ts '2007-06-30 00:00:00.000'} WHERE ("No_"='70105') AND ("timestamp"<=0x000000000001A698)
Friday, 22 June 2007
Default Costing Method
Update Base Unit of Measure in Item Card
- Sales Unit of Measure
- Purch. Unit of Measure
Create Item
| Field No. | Field Name | Value |
| 1 | No. | 70105 |
| 15 | Allow Invoice Disc. | Yes |
| 19 | Price/Profit Calculation | Profit=Price-Cost |
| 21 | Costing Method | FIFO |
| 29 | Cost is Adjusted | Yes |
| 30 | Allow Online Adjustment | Yes |
| 97 | No. Series | ITEM2 |
| 100 | Reserve | Optional |
| 5417 | | Manual |
| 5419 | Replenishment System | Purchase |
| 5422 | Rounding Precision | 1 |
| 5440 | Reordering Policy | |
| 7384 | Use Cross-Docking | Yes |
| 99000773 | Order Tracking Policy | None |