Production BOM - list of components needed to make an item.
Routing Link - Operation steps used to make the item.
End Product - Finished goods or subassembly produced from the operating steps in routing link.
Showing posts with label Manufacturing. Show all posts
Showing posts with label Manufacturing. Show all posts
Thursday, 25 October 2007
Tuesday, 15 May 2007
Calculate Standard Cost
Problem:
You have make changes to the material overhead on the BOM and the capacity overhead of one machine center but the cost is not reflected in standard Unit Cost yet.
Solution:
You need to run the Calc. Standard Cost function at the Item Card.
Discussion:
You have make changes to the material overhead on the BOM and the capacity overhead of one machine center but the cost is not reflected in standard Unit Cost yet.
Solution:
You need to run the Calc. Standard Cost function at the Item Card.
Discussion:
- On Item Card, Click Manufacturing --> Calc. Standard Cost.
- In the next window, click Single / All Levels and then click OK.
Create Work Centers
To open Work Centers card, click:
Manufacturing --> Capacities --> Work Centers
1) Press F3 and then Enter to create a new Work Center
2) Enter the relevant information.
Manufacturing --> Capacities --> Work Centers
1) Press F3 and then Enter to create a new Work Center
2) Enter the relevant information.
Friday, 11 May 2007
Setup Cost for Machine Center
Open Machine Center Card. Select Posting Tab.
Fill in the Direct Unit Cost and Indirect Cost % and / or Overhead Rate fields. The Unit Cost field will be calculated automatically.
When you change the Unit Cost, Indirect Cost % or Overhead Rate fields, only the respective fields and the Unit Cost field in Table 99000758 (Machine Center) will be updated.
Fill in the Direct Unit Cost and Indirect Cost % and / or Overhead Rate fields. The Unit Cost field will be calculated automatically.
When you change the Unit Cost, Indirect Cost % or Overhead Rate fields, only the respective fields and the Unit Cost field in Table 99000758 (Machine Center) will be updated.
Machine Center Card
Machine Center Card can be accessed from
Manufacturing --> Capacities --> Machine Center
Manufacturing --> Capacities --> Machine Center
Thursday, 10 May 2007
Capacity Ledger Entries
When we post purchase or sale of items, Item Ledger Entry and Value Entry tables are involved. When items are manufactured, additional Capacity Ledger Entry is involved as well.
Wednesday, 9 May 2007
Manufacturing Cost
Manufacturing cost consist of:
1) Direct Cost (Material and Labor)
2) Indirect Cost
1) Direct Cost (Material and Labor)
2) Indirect Cost
Inventory in Manufacturing comapny
Manufacturing company usually have 3 types of inventory:
1) Raw Material
2) Work In Progress (WIP)
3) Finished Goods
1) Raw Material
2) Work In Progress (WIP)
3) Finished Goods
Wednesday, 18 April 2007
Consumption Journal and Output Journal
There are 2 important journals in Manufacturing module. These are:
1) Consumption Journal - record the usage or material
2) Output Journal - record the quantity produced and time used.
1) Consumption Journal - record the usage or material
2) Output Journal - record the quantity produced and time used.
Friday, 6 April 2007
Work Center Groups, Work Center and Machine Center
Work Center Groups can be considered as a department within the organization such as Production Department, Shipping Department and Inventory Department. Within the work center groups, we can have many Work Centers or Sections, such as Painting, Packaging and Quality Assurance. A work center consist of many machine centers or production line, such as Painting Line 1, Painting Line 2, Painting Line 3, Packaging Line 1, Packaging Line 2 and Quality Assurance 1 and Quality Assurance 2. Machine is the lowest level of entity. Machine center can consist of a single or multiple machines or person. The total capacity of a work center is the sum of the machine centers. Please note that one machine center can only belong to one work center but one work center can have multiple machine centers.
My company only use Work Centers and Machine Centers but not using Work Center Groups.
My company only use Work Centers and Machine Centers but not using Work Center Groups.
Planning Warning
You can set Navision to give you warning if the promised sales quantity cannot be met by production. If a sales line has been planned for production order and you try to change the sales line, Navision will prompt warning message so that you will be more cautious when changing the sales line. Planning warning can be turned on at the Manufacturing Setup window. To open Manufacturing setup window, click Manufacturing --> Setup --> Manufacturing Setup.